SMT Harlingen II
10 MW / 20 MWh · BYD · Fluence · COD 2024
Period comparison
The reason is the point, not the delta
SOC up 1.32 pts vs last week.
Availability analytics
Click any day for root cause, forecast and revenue impact
Harlingen II is at 96.0% availability — 2.0 pts under the 98% Axpo guarantee — because String 3 has been offline 6 days after an inverter trip. On current trend the settlement period closes inside the shortfall penalty band in 11 days (Jul 26). Estimated settlement loss: $480K.
On the current trend the period closes at ~96.0%, triggering the Axpo shortfall penalty band. Settlement closes in 11 days — restoring String 3 now is the only path to clear the band.
Highest-ROI action: restore String 3 and file the availability exception before the Jul 26 settlement close. Expected recovery: $480K — the full penalty band cleared.
Recommendations for this site
Plain English, ranked by impact
Contract position
Money-attached, each figure carries its evidence
Warranty floor trajectory
Measured SOH vs warranted curve vs the contract floor
Open alerts
1 current open findings on this site
String 3 has been offline 6 days after an inverter trip, pulling availability below the 98% floor on the 7-year availability swap.
Digital twin
Container and rack severity · click a flagged rack to open its finding
Rack-level view, kept shallow by design. B9 stays at the contractual and financial layer, not cell diagnostics.